News Brief: the reporting, attributed to the outlet.
Private housing: build quality
Small condos took 28 of 48 low Conquas bands in six years, BCA data show
Small condos, usually under 50 units, made up over 58 per cent of private residential projects rated band 4 to 6 under Conquas in the past six years, according to BCA data reported by The Business Times on 6 July 2026.
Prevo Research · Reported 6 July 2026
Reported by The Business Times (Grace Leong), 6 July 2026
None of the 24 claims in this story matched one of Prevo's records. It is the outlet's reporting, attributed, not confirmed by Prevo.
Published on Prevo 31 October 2026
What happened
Small private condominium projects are more likely than larger ones to score poorly on construction workmanship, according to Building and Construction Authority (BCA) data reported by The Business Times on 6 July 2026. Of 167 projects assessed under Conquas over the past six years, 48 received bands 4 to 6, and 28 of those were small condos, usually under 50 units. That puts small condos at over 58 per cent of low-rated projects. Of the 119 projects in bands 1 to 3, only 17, about 14 per cent, were small projects, the newspaper reported. BCA said band 1 developers had major defects in fewer than one per 1,000 units after TOP, against 80 per 1,000 for band 6 developers.
The Business Times reported that a framework which took effect on 22 May 2026 lets authorities bar developers with severe safety non-compliances or repeated major-defect projects from residential land sales for up to five years. It supplements Conquas, introduced in 1989. Conquas is mandatory for GLS projects and for developers not assessed in the past three years. Developers with a band 4, 5 or 6 project, or with significant major defects in three years, must also be assessed on residential projects.
The newspaper named several developments. Oxley Holdings was rated a band 4 developer, with six of its 11 assessed projects scoring poorly, including the 18-unit Parkwood Residences at band 4 and the 24-unit Sea Pavilion Residences at band 5. Sekon International's 21-unit 33 Devonshire was rated band 5, as was The Carrara on Mountbatten Road, a group of six semi-detached homes. The Straits Times reported that several of the weaker-scoring projects had been marketed as luxury developments.
As reported
In the report by Grace Leong, The Business Times quoted Sing Tien Foo of NUS Business School, who said small projects form a disproportionately large share of poor-quality projects. He linked this to less prefabrication and more on-site work exposed to weather, and to larger projects drawing established contractors. Eric Cheng, founder and chief executive of band 5 developer Sevens Group, said a Conquas score alone does not determine a developer's credibility. In his view, securing BCA approval and TOP is what matters.
Questions
Are small condos more likely to have construction defects in Singapore?
Yes, according to BCA data reported by The Business Times on 6 July 2026. Small condos, usually under 50 units, made up over 58 per cent of projects rated band 4 to 6 under Conquas in the past six years: 28 of 48.
How many projects were assessed under Conquas and how did they score?
BCA assessed 167 projects over the past six years, The Business Times reported. Of these, 119 received bands 1 to 3 and 48 received bands 4 to 6. Only 17 of the higher-rated projects, about 14 per cent, were small projects.
Can developers with poor build quality be barred from land sales?
Yes. Under a framework that took effect on 22 May 2026, developers with severe safety non-compliances or repeated major-defect projects may be barred from residential land sales for up to five years, The Business Times reported.
What was reported
24 claims: 12 reported only, 12 no record identifiedShowHide
Each claim in Prevo's words, as the reporting stated it. None was matched to one of Prevo's records, so none is marked checked.
- No record identifiedBCA data show small private residential projects are more likely than larger ones to score poorly on construction workmanship.
- Reported onlySmall condos, usually under 50 units, made up over 58 per cent of low-rated private residential projects in the past six years.no kind of Prevo record holds this claim
- Reported only167 projects were assessed under Conquas during the period; 48 got bands 4 to 6, of which 28 were small condos.no kind of Prevo record holds this claim
- Reported only119 projects got bands 1 to 3; only 17 of them, about 14 per cent, were small projects.no kind of Prevo record holds this claim
- Reported onlyBand 1 developers had major defects in fewer than one per 1,000 units after TOP; band 6 developers had 80 per 1,000.no kind of Prevo record holds this claim
- No record identifiedDevelopers with severe safety non-compliances or repeated major-defect projects may be barred from residential land sales for up to five years.no Prevo event for this change: a candidate event
- No record identifiedThe framework took effect on May 22, supplementing Conquas to deter errant developers and protect home buyers.no Prevo event for this change: a candidate event
- Reported onlyConquas, introduced in 1989, is mandatory for GLS projects and for developers not assessed in the past three years.no kind of Prevo record holds this claim
- Reported onlyDevelopers with a band 4, 5 or 6 project or significant major defects in three years must also undergo Conquas for residential projects.no kind of Prevo record holds this claim
- Reported onlyBandings rest on BCA inspection non-compliances, including waterproofing tests, and validated homeowner reports of major defects after TOP.no kind of Prevo record holds this claim
- Reported onlyStraits Times checks found several weaker-scoring projects had been marketed as luxury developments.no kind of Prevo record holds this claim
- No record identifiedThe Carrara on Mountbatten Road, six semi-detached homes, received a band 5 Conquas rating.
- No record identifiedEric Cheng says a Conquas score alone does not determine developer credibility; securing BCA approval and TOP is what matters.
- No record identifiedSevens Group was rated a band 5 developer.
- No record identifiedSekon International's 21-unit 33 Devonshire was rated band 5, and Sekon was also a band 5 developer.
- No record identifiedSix of Oxley Holdings' 11 assessed projects scored poorly; Oxley was rated a band 4 developer.
- No record identifiedOxley's 18-unit Parkwood Residences received a band 4 rating.
- No record identifiedOxley's 24-unit Sea Pavilion Residences received a band 5 rating.
- No record identifiedAffinity at Serangoon, Kent Ridge Hill Residences and 1953 Balestier scored band 4; The Verandah Residences was rated band 5.
- No record identifiedOther Oxley projects scored better: two rated band 1, Mayfair Gardens and Mayfair Modern band 2, Sixteen 35 Residences band 3.
- Reported onlyThe Straits Times asked Sekon International and Oxley Holdings for comment, with no response reported.no kind of Prevo record holds this claim
- Reported onlySing Tien Foo says small projects are a disproportionately large share of poor-quality projects despite being a small share overall.not checked: an opinion
- Reported onlySing says small projects use less prefabrication and more on-site work exposed to weather, raising defect likelihood.not checked: an opinion
- Reported onlySing says premium materials cannot offset poor installation; large projects may draw established contractors using more mechanisation and experienced workers.not checked: an opinion