Singapore, planning
Preparatory works for the Long Island coastal protection project to start from end-2026
URA announced that preparatory works for Long Island, a coastal protection project off the East Coast, will commence from end-2026, with HDB as the appointed reclamation agent.
- Announced
- 30 June 2026
- In effect from
- No single effective date recorded
- Importance
- Medium
Evidence checked. 11 of 11 claims checked against a held source. Primary-source confirmation is pending for 11. Primary sources last checked 18 November 2026.
Sign in to save this event to your research. It is free.
What changed, in brief
URA announced that preparatory works for Long Island, a coastal protection project off the East Coast, will commence from end-2026, with HDB as the appointed reclamation agent. The works will run in two phases: about 570 ha west of Bedok Jetty from end-2026, and about 155 ha east of Bedok Jetty only after major events including the SEA Games in 2029. The Environmental Study report is open for public feedback for four weeks from 30 June 2026. Main reclamation works will only start after further technical studies and public engagement.
What you can do next
What changed
When it applies
- 30 June 2026Announced
Where it applies
Covers preparatory works (seabed obstruction removal, temporary sand bunds and sand infilling) in the waters off the East Coast, at least 130m from the shoreline. Does not cover the main reclamation works for Long Island, whose final reclamation profile is not yet determined. The release does not set out any housing, land use allocation or property rule changes.
Market context
The market around the announcement
When this was announced on 30 June 2026, URA's latest quarterly figures were for 1Q2026, published 24 April 2026, 67 days earlier. The next release, 2Q2026, came on 24 July 2026. The table carries on through two releases after it.
Swipe the table sideways for every quarter
| Private residential | 3Q2025Oct 2025 | 4Q2025Jan 2026 | On the day1Q2026Apr 2026 | 2Q2026Jul 2026 | 3Q2026Oct 2026 | Trend | Change1Q2026 to 3Q2026 |
|---|---|---|---|---|---|---|---|
| Prices | |||||||
| Private home price index | 215.1 | 216.4 | 218.3 | 219.4 | 222.5 | +1.9% | |
| Non-landed, core central region | 163.4 | 157.7 | 158.6 | 161.5 | 162.0 | +2.1% | |
| Private rental index | 161.7 | 160.9 | 161.4 | 162.5 | 164.6 | +2.0% | |
| Sales | |||||||
| New homes sold by developers | 3,288 | 2,940 | 2,013 | 2,141 | 1,183 | −41.2% | |
| Resales | 3,881 | 3,529 | 3,225 | 3,813 | 3,801 | +17.9% | |
| Sub-sales | 235 | 230 | 175 | 194 | 162 | −7.4% | |
| Units launched | 4,191 | 2,632 | 1,844 | 1,783 | 1,140 | −38.2% | |
| Supply | |||||||
| Unsold, uncompleted, with planning approval | 17,029 | 14,859 | 16,095 | 14,929 | 18,853 | +17.1% | |
| Pipeline with planning approval | 36,814 | 35,690 | 38,133 | 38,556 | 40,252 | +5.6% | |
| Vacancy rate | held | 6.0% | 6.2% | 6.4% | 7.2% | +1.0 pts | |
Each figure is the quarter's own value as URA printed it in that quarter's release, not as later revised. Select a figure to see the annex and page it comes from.
Held back: URA prints the number in more than one place and the table's labels do not settle which one it is, so the archive stores it but does not show it.
Sources and verification
Full event recordDates, regulator, scope, every stored claim value, the position before and the current status
Event facts
- Announced
- 30 June 2026
- Instruments and scope
- Covers preparatory works (seabed obstruction removal, temporary sand bunds and sand infilling) in the waters off the East Coast, at least 130m from the shoreline. Does not cover the main reclamation works for Long Island, whose final reclamation profile is not yet determined. The release does not set out any housing, land use allocation or property rule changes.
- Current status
- Active as introduced, no amendment recorded in this archive.
Evidence behind this event
11 claims, 11 verified
- Standalone causal impact
- Not identified
Each outcome's causality grade rates how strongly it is attributed to this policy. None is a formally identified causal effect.
Every claim, by type
Rates, figures and counts3
- Claim 4
The first phase starts in end-2026 west of Bedok Jetty and covers about 570 ha.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 4. Passage: "The first phase will start in end-2026 and will be carried out in the waters west of Bedok Jetty. The first phase will cover an area of approximately 570 ha"] - Claim 5
The first phase spans around 7km east to west and up to 1km north to south.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 4. Passage: "it will span around 7km in length from east to west, and up to 1km wide from north to south"] - Claim 6
The second phase east of Bedok Jetty covers about 155 ha.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 5. Passage: "The second phase of preparatory works will be carried out in the waters to the east of Bedok Jetty, and will cover an area of approximately 155 ha."]
Policy decisions and design3
- Claim 2
HDB is the appointed reclamation agent for Long Island.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 1. Passage: "The Housing & Development Board (HDB), the appointed reclamation agent for ‘Long Island’, will implement measures to mitigate the impact of preparatory works"] - Claim 3
The preparatory works will be at least 130m from the shoreline and primarily involve seabed obstruction removal, temporary sand bunds and sand infilling.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 3. Passage: "primarily involve the removal of seabed obstructions, followed by the construction of temporary sand bunds and sand infilling. The works will be at least 130m away from the shoreline"] - Claim 10
Main reclamation works will only commence after technical studies, mitigation measures and further public engagement are completed.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 12. Passage: "The main reclamation works for ‘Long Island’ will be undertaken later and will only commence after agencies have completed the relevant technical studies, determined mitigation measures, and reviewed and incorporated feedback from further public engagements."]
Dates4
- Claim 1
Preparatory works for Long Island will commence from end-2026.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 1. Passage: "Preparatory works for ‘Long Island’, Singapore’s large-scale critical coastal protection strategy, will commence from end-2026."] - Claim 7
The second phase will only commence after major events including the SEA Games in 2029, with the start date to be shared later.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 5. Passage: "the second phase will only commence after the completion of these events. More details on the commencement date of the second phase will be shared when ready."] - Claim 8
The Environmental Study report is open for public feedback for four weeks from 30 June 2026.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 10. Passage: "The Environmental Study report is available for public feedback for four weeks from 30 June 2026."] - Claim 11
The next phase of public engagement on Long Island will begin from end-2026.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 13. Passage: "agencies will begin the next phase of public engagement from end-2026."]
Characterisations and comparisons1
- Claim 9
The area used for preparatory works does not reflect the future land profile of Long Island.
VERIFIED PRIMARY[Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 11. Passage: "The area that is used for preparatory works is not reflective of the future land profile of ‘Long Island’."]
How this is scored
Counts are by provenance, meaning who established the claim, not by how confident we are. A policy fact is one the regulator's own document states. A market observation comes from a named data series. A derived calculation is one we computed, with the working recorded on the claim.
Interpretations are counted, never netted out. This page will not display zero unsupported claims while interpretive sections sit outside the claim ledger, because that number would be true only by excluding the material most likely to be wrong.
A claim of one type is only treated as verified by a source of the matching type. A market observation is not verified by a regulator press release.
Claims are grouped by the type recorded on each one. Grouping hides nothing: every claim is in exactly one group, in full.
Sources
1 document
Primary sources1
- Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community
Urban Redevelopment Authority · Published 30 June 2026
Original source link unavailable
Cited by 11 claims, 11 verified
- Claim 1 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 1. Passage: "Preparatory works for ‘Long Island’, Singapore’s large-scale critical coastal protection strategy, will commence from end-2026."
- Claim 2 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 1. Passage: "The Housing & Development Board (HDB), the appointed reclamation agent for ‘Long Island’, will implement measures to mitigate the impact of preparatory works"
- Claim 3 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 3. Passage: "primarily involve the removal of seabed obstructions, followed by the construction of temporary sand bunds and sand infilling. The works will be at least 130m away from the shoreline"
- Claim 4 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 4. Passage: "The first phase will start in end-2026 and will be carried out in the waters west of Bedok Jetty. The first phase will cover an area of approximately 570 ha"
- Claim 5 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 4. Passage: "it will span around 7km in length from east to west, and up to 1km wide from north to south"
- Claim 6 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 5. Passage: "The second phase of preparatory works will be carried out in the waters to the east of Bedok Jetty, and will cover an area of approximately 155 ha."
- Claim 7 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 5. Passage: "the second phase will only commence after the completion of these events. More details on the commencement date of the second phase will be shared when ready."
- Claim 8 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 10. Passage: "The Environmental Study report is available for public feedback for four weeks from 30 June 2026."
- Claim 9 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 11. Passage: "The area that is used for preparatory works is not reflective of the future land profile of ‘Long Island’."
- Claim 10 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 12. Passage: "The main reclamation works for ‘Long Island’ will be undertaken later and will only commence after agencies have completed the relevant technical studies, determined mitigation measures, and reviewed and incorporated feedback from further public engagements."
- Claim 11 · Urban Redevelopment Authority (URA) release "Preparatory works for ‘Long Island’ project to commence from end-2026; measures to be implemented to mitigate impact on the environment and community", 30 June 2026, paragraph 13. Passage: "agencies will begin the next phase of public engagement from end-2026."
Event checked against its primary sources on 18 November 2026. Each claim keeps its own verification status.
Prevo provides research and informational analysis only. It is not a broker, investment adviser or fiduciary, and nothing on this site constitutes investment, legal, tax or financial advice. Verify independently.